Torrance approves $35.9 million design‑build contract for transit center parking structure
Summary
The City Council voted unanimously to award a design‑build contract to McCarthy Building Companies for a four‑story, roughly 1,000‑space parking structure at the Torrance Regional Transit Center. The contract is $32,662,154 with a 10% contingency, and staff said the project aims to be ready for the LA 2028 Olympics.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
The Torrance City Council on Tuesday approved a design‑build agreement for a four‑story, approximately 1,000‑space parking structure at the Torrance Regional Transit Center, awarding the contract to McCarthy Building Companies Inc.
Milton Soudaubry, general services department, told the council staff selected McCarthy as the highest‑ranked proposer following a competitive procurement and recommended the award. "This project will significantly expand parking capacity at the transit center, improve access and convenience for transit users, and support the city's long‑term transportation and mobility goals," Soudaubry said.
Staff presented a contract price of $32,662,154 and recommended a 10% contingency. Councilmember Jeremy Gerson moved the staff recommendation, which passed unanimously. The motion as read by the council set a not‑to‑exceed total of $35,928,369.40 and a three‑year construction window beginning July 21, 2026, and ending July 20, 2029.
During the discussion, staff described the likely mix of funding sources as including previously awarded regional (Metro) funds, a portion from the general fund and potential contributions from the transit enterprise fund. "We will continue to work with Metro and regional partners to identify external funding for the balance of the project," said Adam Chaparazzi, who spoke for project operations and schedule, adding the city aims to complete work in time for the LA ’28 Olympics.
Several council members emphasized sustainability and operations. Councilmember Kartsounis urged pursuing rooftop solar grants and earlier installation because of impending grant deadlines; Soudaubry replied the project includes infrastructure capability to support a solar installation in the future and staff will continue to pursue grant opportunities. Councilmember Sheikh asked about overnight parking and security; staff said the project scope includes a parking management plan, coordination with the Torrance Police Department and safety measures.
The contract also authorizes a first amendment to the owner's representative services agreement with MOCA Systems Inc. to continue providing owner representation through construction.
What happens next: staff will return to council with funding options and further implementation details; construction is scheduled to begin per the approved contract period and staff reiterated the city's goal of delivering the structure ahead of the 2028 Olympics.