Commissioners approve mileage correction for Steve Miller Road after highway update
Summary
Highway superintendent reported permit delays on Bridge 39, permit revisions at Radcliffe Road/Highway 150 and recommended correcting Steve Miller Road's recorded length; the commission voted by voice to approve the mileage correction.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The highway superintendent told the Washington County commissioners about permit delays for Bridge 39 and design revisions for the Radcliffe Road/Highway 150 intersection and asked the board to approve a mileage correction on Steve Miller Road.
The superintendent said Bridge 39 permits should be requested by Aug. 7 with expected responses within 30 days and that construction likely will await utility relocation and start in spring 2027. He reported NDOT requested design changes on the Radcliffe Road intersection; HWC Engineering is preparing those revisions.
On a separate matter, staff recommended changing the recorded length of Steve Miller Road (IR 174) from 0.3011 miles to 0.4282 miles — a correction of +0.1271. A commissioner moved and another seconded the recommendation; the chair called for aye and the motion carried by voice vote.
The highway superintendent also reviewed recent emergency and patching work in small towns: a Little York culvert repair that produced an invoice for $4,904.88 (the town reimbursed the county) and a separate short patching job near Hardinsburg totaling around $970 in materials. Staff emphasized the need to clarify policy when the county performs work in incorporated towns to avoid audit exposure.
Next steps: staff will follow up on permit timelines for Bridge 39 and Radcliffe Road and will file the mileage correction with the state as recommended.