Suffield WPCA reports delinquent sewer balance of $149,840 and operational upgrades completed

Suffield Water Pollution Control Authority & Treatment Facility · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At its July 14 meeting the WPCA reviewed treasurer and staff reports showing $149,840.14 in delinquent sewer charges, a June 2026 collection rate of 94.96% (down from 97.77% in June 2025), and operations updates including an emergency force-main repair and new VFDs and transfer switches at multiple pump stations.

The Suffield Water Pollution Control Authority on July 14 reviewed finance and operations updates from the treasurer and superintendent.

Treasurer Todd Mervosh reported administration bills and RCM bills: Administration (O&M) 2025/26 $100,811.53 and 2026/27 $69,535.59; RCM bills 2025/26 $444,378.54; administration fund distribution (June payroll) $77,362.95. John Murphy moved to approve the treasurer's report, Nick Shute seconded, and the motion passed unanimously.

The business administrator reported the total delinquent amount through June as $149,840.14, of which $115,204.09 is the 2025 sewer usage bill. The minutes record the June 2026 collection rate as 94.96% compared with 97.77% in June 2025. Annual sewer bills were mailed and the last day to pay noted in the packet is July 31, 2026.

Superintendent Jamie Kreller provided operational items: the WPCA recorded 42 dry tons in June (below the monthly solids allotment under the MDC agreement); operators completed an emergency repair after a force main failure inside the wet well at pump station 18 (Wisteria Lane); new variable-frequency drives at pump station 1 (Thompsonville Road) were completed; and new transfer switches were installed at pump stations 4 (Deep Brook Harbor), 8 (Plantation Drive), and 9 (Conservation Drive). Kreller also attended an EPA Region 1 FY26 Community Grants presentation.

The minutes do not record public comment on these items. The authority did not provide a breakdown of delinquent accounts by parcel type or indicate follow-up enforcement action in the minutes; the packet is available from the WPCA on request.