Mount Angel council approves 10-year Comcast franchise; company outlines timeline
Summary
The council approved a 10-year franchise agreement with Comcast of Oregon after staff recommendation. Comcast’s government affairs director said design work would begin once the franchise is effective and construction could follow within roughly 18 months, with some services and affordability programs available to residents.
Get email alerts on the Telecom topic
No spam. Unsubscribe anytime.
The Mount Angel City Council voted Sept. 6 to approve a 10-year franchise agreement with Comcast of Oregon, clearing the way for the cable and broadband provider to design and eventually construct service infrastructure in the city.
Staff summarized the multi-year negotiation and recommended approval of the franchise agreement drafted by city counsel and negotiated with Comcast. "Comcast initially reached out to the city of Mount Angel in February 2021," a staff member said, and the negotiated draft was brought before council after review by city attorneys.
Tim Goodman, senior director of government regulatory affairs for Comcast, told the council the company would begin design work after franchise approval. "Once we have those (designs), we will begin for us to move forward," Goodman said. He pointed to a recent franchise the company completed in Estacada and suggested a roughly 18-month build timeline from franchise effectiveness there, though he said Mount Angel’s proximity to other construction could shorten that schedule.
Goodman reviewed services Comcast intends to offer, including broadband, video and expanded mobile/home security products. He also described Comcast’s low-cost assistance program, saying the company’s Internet Essentials product has offered qualifying households a discounted service for years and that connectivity programs supported by the Federal Communications Commission may provide further options for eligible residents.
Councilors asked practical questions about construction methods and routing. Goodman said Comcast typically uses aerial placement where existing poles are available and directional boring rather than open trenching when underground methods are required. He said trenching would be rare except where individual service drops require it.
Following the discussion, a councilor moved to approve the franchise agreement; the motion was seconded and passed by roll call.
The agreement authorizes Comcast to operate in the public right-of-way under the terms presented to council and sets a 10-year franchise term. Council members said they had a few technical clarifications to resolve with staff but that those items would not change the substantive terms of the franchise.
The city will now complete the administrative steps required to execute the franchise. Comcast representatives said they would follow up with staff and remain available to answer questions about construction timing, service offerings and community programs.
What happens next: Comcast will begin design work once the franchise is effective; construction and service activation timelines depend on permitting and design completion.