Summary

Staff introduced the FY26–36 capital investment plan: bond-funded school replacements (Carrboro, Estes Hills), high-priority maintenance (roof phases at East Chapel Hill HS and Carrboro), and recurring capital uses; staff explained why trailers exist (pre-K requirements, temporary capacity) and noted some trailers are unoccupied but maintained.

The district presented its FY26–36 Capital Investment Plan (CIP), explaining project sequencing, funding buckets and near-term priorities. Mr. Scirochi described three funding buckets: bond-funded school replacements, high‑priority maintenance, and other capital uses (recurring capital and Article 46 sales-tax funds). He said the 10‑year plan includes remaining bond capacity, PAYGO, and county-limited obligation financing for maintenance work.

Near-term projects in the plan include continued construction phasing for Carrboro Elementary (FY year 2), design funds for Estes Hills Elementary with construction requested in FY28, and high‑priority maintenance such as multi‑year roof replacements at East Chapel Hill High School and Carrboro Elementary. Mr. Scirochi also noted a smaller project to replace portable air conditioning at Scroggs Elementary.

Board members probed the role of trailers (modular units). Mr. Scirochi said trailers are used to meet program and regulatory requirements (notably pre‑K bathrooms and direct exterior egress) and to respond to short‑term capacity fluctuations; he also acknowledged district goals to minimize trailer use when possible and cautioned that removing trailers reduces classroom capacity and can affect program placements.

Public commenters reiterated that some schools use trailers for pre‑K and asked staff to clarify how pre‑K enrollment is counted against capacity. The CIP presentation will be transmitted to the county for annual appropriation decisions; the board and staff will continue refining sequencing and cost estimates.