Council approves $2.8M GMP for downtown South Lake/Cherry streetscape project

City of Groveland City Council · July 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a guaranteed maximum price contract amendment with Traverse Group, Inc. for Phase II of the South Lake Avenue and Cherry Street streetscape and stormwater project, funded by grants and CRA funds and scheduled to start July 7, 2026.

Groveland's City Council approved a contract price amendment July 6 with Traverse Group, Inc. to begin Phase II construction of the South Lake Avenue and Cherry Street Streetscape and Stormwater Project.

Community Redevelopment Agency Manager Frank Calascione said the design and permitting work already invested totaled roughly $500,000 and that the Phase II construction GMP is approximately $2.8 million. Funding includes grant awards (Florida Commerce CDBG and FDEP stormwater grant) and CRA funds; Calascione said the project will be constructed in three phases over an estimated 150 days with a construction start date of July 7, 2026.

Mayor Keogh asked about GMP structure and whether contingency savings would benefit the City; staff said the GMP sets the City's maximum obligation and that cost overruns would be the contractor's responsibility. Council expressed interest in reviewing CRA obligations in an upcoming CRA budget workshop before spending additional CRA funds. After the presentation, the motion to approve the contract amendment passed unanimously.