Boulder council approves Amendment 2 for Phase 1 water project; OKs Well 4 abandonment change order

City Council · February 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Boulder City Council approved Amendment 2 to the Phase 1 Water System Improvements project and authorized a $4,720 change order to abandon Well 4. The state is proposing 75% loan forgiveness for the new well, which council said would leave the city with an estimated out‑of‑pocket cost of about $300,000.

Boulder’s City Council voted Feb. 18 to approve Amendment 2 to the Phase 1 Water System Improvements project and to authorize a $4,720 change order to abandon Well 4.

City Engineer Elly Schmeltzer told the council the easement with the Montana Department of Public Health and Human Services for Well 5 is in place and that Amendment 2 covers a new well. Schmeltzer said the project budget was “in good shape” and that the state is proposing 75% loan forgiveness, which would leave the city with an estimated out‑of‑pocket cost of roughly $300,000. Bids for the new well are scheduled to be received on March 11.

Schmeltzer also said Well 4 abandonment was not in O'Keefe’s original scope of work and, because of impending legislative changes, needed to be completed sooner. Council approved O'Keefe’s change order for the abandonment work in the amount of $4,720. Both motions carried with three aye votes.

Dawson moved to approve Amendment 2; Taylor seconded. Dawson moved to approve the O'Keefe change order; Taylor seconded. The minutes do not record individual roll‑call votes by name, only that each motion carried with three ayes.

Next steps include receipt of bids for the new well on March 11 and continued project management by city staff and the engineering consultant. The council did not specify a timeline for when loan documents or final funding decisions will be executed.