Public Works briefs Select Board on East Main Street corridor design; board gives feedback on path width, safety and right‑of‑way
Summary
Public Works Director Chris Pant presented the 25% design for the East Main Street Corridor shared‑use path (projected construction cost ~$8.2M, design funded by Chapter 90). Board members discussed 8‑ vs. 10‑foot path widths, buffers, underpass details, hawk signals, and encroachment/ROW processes; staff will consolidate comments for the designer and MassDOT review.
Get email alerts on the East Main Corridor topic
No spam. Unsubscribe anytime.
Chris Pant, the town’s director of public works, gave a stage‑setting briefing on the East Main Street Corridor project’s 25% design submission and outlined the process for consolidating departmental comments before a designer‑level reconciliation meeting with MassDOT. The proposed corridor would extend from Hastings School toward Thomas Newton Drive, add a shared‑use path (the design seeks an 8‑foot path with a 2‑foot asphalt buffer rather than grass) and address the East Main/Flanders intersection for improved safety.
Key points discussed included the tradeoff between an 8‑foot path (requested for right‑of‑way and cost reasons) and a 10‑foot multi‑use path favored by the ATSC for higher‑volume commuter use; the board asked the design team to evaluate hawk or similar crossing signals under the Route 9 underpass, consider guardrails or delineators where space is tight, and clarify how MassDOT will handle property encroachments and acquisition. Pant said construction is currently estimated at about $8.2 million and that design expenses are town‑funded (Chapter 90) and run about $900,000 to completion.
Why it matters: The corridor is a significant capital project that changes pedestrian/bike connectivity. Width, buffer and crossing choices will affect cost, property impacts, safety and whether the path functions as a local walkway or a higher‑speed commuter route.
What happens next: Staff will collect the Select Board’s comments and forward them to the designer and MassDOT; a formal design public hearing is expected in the fall as the project advances.