Green tee interchange planned for Lake Caroline; construction eyed for "summer 28"
Summary
Project presenters described a planned green tee interchange at the eastern Lake Caroline entrance, outlined a schedule for conceptual and field inspection plans, and said construction is estimated for "summer 28," pending utility relocation and right-of-way acquisition.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Project presenters outlined plans for a green tee interchange at the eastern entrance to Lake Caroline and estimated construction could begin "summer 28," subject to utility relocation and right-of-way acquisition.
The project team said the interchange will include a free-flow eastbound lane that allows merging traffic to use a separate lane, reducing the stop-and-go congestion that now forms at the entrance. "So it just kind of helps traffic just keep moving," the presenter said, describing the intended traffic flow.
The team is currently working from a conceptual layout, with conceptual plans scheduled for submission to a reviewer named Tim in "the first part of August," and field inspection plans targeted toward the end of the third quarter, the presenter said. He added the design team expects to reuse much of the work from a prior five-lane project to shorten the overall schedule. "We'll be able to reuse a lot of the work we did on the five lane project to help shorten the time frame," he said.
Attendees asked for clearer visual materials after the meeting PDF proved hard to read. "If you would make us a map, that's showing where the green tee is," one committee member requested; the presenter agreed to provide a different map format and to send it to Tim.
When asked about the construction start, the presenter estimated "summer 28" and explained that the timeline depends on utility relocations and securing right-of-way. He said the team hopes to have right-of-way by the next summer, but underscored those steps remain pending.
Another participant noted recent design changes had compressed the schedule for the designers: "Remember, we changed their project up on them, so they've only had a month or so to redo their design," the participant said, highlighting why the project team was behind relative to others.
Next steps: the project team will prepare a clearer map for distribution to reviewers, submit conceptual plans in the first part of August, and pursue field inspection plans toward the end of the third quarter. Construction timing remains contingent on utility relocation and right-of-way acquisition.