Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure Sewer topic

No spam. Unsubscribe anytime.

Anamosa council approves Ford and Huber sanitary sewer contract amid resident questions

City Council of the City of Anamosa · May 27, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Anamosa City Council awarded the Ford and Huber Sanitary Sewer Project contract to Tschiggfrie Excavating Co. after an HR Green update and a brief public comment; the motion passed 4–2 with two council members opposed.

The Anamosa City Council voted to award the Ford and Huber Sanitary Sewer Project contract to Tschiggfrie Excavating Co. following an engineering recommendation and a public hearing on May 27, 2025.

Mayor Rod Smith opened the hearing at 6:09 P.M.; resident Aleshia Chambers, who lives on North Huber Street, provided comments and HR Green delivered a project update. After discussion, Council member Kay Smith moved, and Council member Todd Weimer seconded, approval of HR Green’s recommendation to accept bids and award the contract to Tschiggfrie Excavating Co. The motion carried with Ayes from Teresa Tuetken, Weimer, Rich Crump and Kay Smith and Nays from Dan Smith and Brooke Gombert.

The council record shows the decision followed the consultant recommendation; the transcript does not specify the contract price, schedule, or funding source. The council did not state any additional conditions in the motion that day.

Next steps: the city will proceed with contracting and project implementation per the consultant recommendation and awarded bidder; the transcript does not specify a construction start date or funding breakdown.