Commissioners approve resurfacing award, accept 11.6‑mile paving grant and OK bridge design contract
Summary
The county engineer recommended awarding a 2026 resurfacing contract (about 4.1 miles) to the apparent low bidder at $650,587.15, asked the board to accept a grant to pave 11.6 miles (federal funds administered by ODOT, construction expected after 07/01/2030), and requested approval of a DLZ Ohio consultant agreement to design two bridge replacements with a base fee of $201,319.
Get email alerts on the Infrastructure Paving topic
No spam. Unsubscribe anytime.
County engineer Adam Gove told commissioners the apparent low bid for the 2026 asphalt resurfacing project (about 4.1 miles on Middle Belleville Road and Reinhardt Road) was $650,587.15, compared with an engineer’s estimate of $618,091.70. He said the bid is within the legal allowance (the county may award up to 20% over the estimate) and recommended awarding the contract.
Gove also asked the board to accept a grant the county received through the County Engineers Association, administered by the Ohio Department of Transportation, to pave about 11.6 miles on Pleasant Valley Road, Pleasant Hill Road, a portion of McCurdy and a portion of Hanley West Road. He said the project is a federal fiscal ’31 project, with construction expected after 07/01/2030, and that ODOT will administer the funds.
On bridges, Gove said the county received five letters of interest for design work and negotiated with DLZ Ohio. He recommended a consultant agreement with a base design fee of $201,319 plus $4,660 in anticipated additional fees to design replacements for Rock Road and Lost Run Road. Gove said the construction costs for those two bridges were likely in the $600,000–$700,000 range and noted an OPWC grant would likely cover about 50% of construction.
Commissioners moved and approved the resurfacing award, accepted the paving grant and approved the DLZ consultant agreement; roll-call votes were recorded as ‘yes.’ Reporters and a member of the public asked follow-up questions about scheduling and detailed construction cost estimates; Gove said he would provide more precise construction numbers via email or text upon request.