Proctor schedules GPR scan and authorizes grout work for fire station floor repair
Summary
Engineers recommended GPR scanning of the fire station floor on Oct. 21 before grout work; grout is expected to take about three days at an estimated cost of $21,884, according to the Selectboard packet.
Get email alerts on the Fire Station topic
No spam. Unsubscribe anytime.
Proctor’s Selectboard recorded an engineer’s recommendation on Oct. 15 to perform ground-penetrating radar (GPR) scanning of the fire station floor before grout work, and the board was given a contractor cost estimate for the grout stage.
According to the Selectboard packet, GPR scanning of the fire station floor was scheduled for Oct. 21, 2024. The engineer anticipates the grout portion of the repair will take about three days and estimated the grout work at $21,884.00. The packet indicates the GPR scan will be completed before grout work begins.
The meeting record lists this work as a next step in the fire station project; the Town Manager will coordinate contractors and project managers for remaining tasks. No formal contract award was recorded in the minutes; the engineer's schedule and cost estimate were presented as project next steps.