Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Northgate Investments topic
No spam. Unsubscribe anytime.
Northgate requires more than $500,000 in upgrades; EDC considers funding and tenant plans
Summary
Director Bryan Belliveau told the board that required fire pumps and tank storage would cost about $200,000 and sprinkler upgrades about $323,000—more than $500,000 total—prompting discussions of CDBG, bank loans, and CEI help; tenant expansion plans and lease decisions were also discussed.
Get email alerts on the Northgate Investments topic
No spam. Unsubscribe anytime.
At the March 10 meeting, the Skowhegan Economic Development Corporation reviewed capital needs at the Northgate property, including a set of sprinkler and water‑supply upgrades that together top $500,000.
Director Bryan Belliveau told the board that fire pumps and tank storage to address insufficient water flow would cost roughly $200,000, and sprinkler upgrades for higher‑hazard uses were estimated at $323,000, bringing combined costs to more than $500,000. Belliveau said roofing and siding repairs would add to the overall project price, and that parking lot sealing and restriping remain on the capital improvement list.
The board discussed funding avenues. Members suggested applying for Community Development Block Grant (CDBG) funding, pursuing a commercial bank loan, or seeking assistance from Community Enterprise entities; Chairman Matt DuBois noted that some banks may offer special rates tied to a deposit relationship. Belliveau identified a contact at CEI, Kristina Cannon, and said he planned a meeting with a contractor on Friday to scope a high‑level capital project.
Separately, DuBois and Belliveau reviewed potential tenant expansion at Northgate for Maine Cedar Hot Tubs, Maine Wood Heat and Genplex and the build‑out work needed to create new space. Belliveau said he would give representatives identified as Scott and Nahum until the next meeting to confirm their intentions so the board can set lease rates and space plans.
The board did not approve specific funding or construction work at the meeting; next steps include the contractor meeting and follow‑up at a subsequent meeting.
