Council authorizes eminent-domain proceedings for parcel tied to railroad-safety grant to preserve quiet zone
Summary
Burlington’s council approved a resolution to begin eminent-domain proceedings to acquire property interests near the Jefferson Street/BNSF crossing to enable signal-arm and crossing work tied to a federal Section 130 grant; staff said BNSF attempted to buy the parcel but could not, and the work helps preserve the city’s quiet zone.
Get email alerts on the Eminent Domain topic
No spam. Unsubscribe anytime.
The Burlington City Council on July 20 authorized proceedings to acquire property interests by eminent domain for the Main Street/Jefferson Street railroad crossing, a step staff described as necessary to install signal arms and other safety equipment under a federal grant program.
Staff told the council the parcel involved is adjacent to the railroad near a bakery and described the area in the resolution as roughly "173 square foot". Staff said the acquisition is intended to allow the city and BNSF to install new signal arms and associated improvements and that the work will also support retention of the city’s quiet zone. According to staff, the acquisition will be funded through a federal Section 130 railroad-safety grant that is administered through the city and reimburses the city for eligible costs.
Staff said BNSF attempted direct purchase negotiations with the property owner but was unsuccessful, and the timetable for the grant requires the city to complete acquisition steps before the grant window closes. Council members asked clarifying questions about the scope and timing of the work, and staff said additional details and appraisal work are underway.
Council approved the resolution to authorize the city to proceed with the acquisition process. Staff said further clarifications about whether a permanent easement or full fee acquisition will be used will be provided in the coming weeks as appraisals and discussions continue.
Next steps: Staff will complete an appraisal, finalize acquisition terms and return with any additional documents required for purchase or easement conveyance and for contract work associated with the railroad-crossing improvements.