Council OKs up to $12,000 from city for backup transformer to protect elevator service

Plankinton City Council · April 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Plankinton council approved a maximum $12,000 city contribution toward a backup transformer for the elevator after staff presented options and cost estimates; any additional upgrades would be paid by the elevator owner.

Plankinton’s City Council voted to authorize a city contribution of up to $12,000 for a backup transformer to protect the town’s elevator service. The vote followed a presentation by public-works staff on electrical options and cost estimates.

Staff member (Public Works) told the council that a full new-service install would cost an estimated $60,878.39 and that a dedicated backup transformer—depending on the configuration—would cost roughly $7,700 to $10,147. “I was recommending $100 per hour for all of our equipment,” the staff member said, describing a proposal to standardize equipment rates and to set consistent labor charges for future insurance or reimbursement claims. He said labor costs in regular hours would likely be in the $70–$80 range and that after-hours rates would be higher.

Council members discussed whether the city should pay the full cost of creating a new service or instead offer cost-sharing so the elevator operator would carry the bulk of any upgrade beyond a simple backup transformer. After questions and clarification from staff and council, a motion to authorize a city contribution not to exceed $12,000 for a backup transformer — with any additional work or a full new service to be paid by the elevator owner — passed.

The motion was recorded in the meeting as coming from Jim with Nathan seconding; the motion carried. Staff said it will draw up a resolution and return a final proposal to the council in May, including precise billing rates and any contract language needed to invoice insurance or third parties.

What happens next: staff will prepare a draft resolution implementing the equipment-rate policy and documenting the city’s $12,000 cap for the backup transformer; the council will consider the resolution at the May meeting.