Council awards Burlington Road reconstruction contract after bids come in below estimate

Oskaloosa City Council · July 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved awarding the Burlington Road reconstruction contract to the low bidder; staff said the low bid of $893,853 is about 17.6% below the engineer's estimate and recommended a $65,000 contingency and a notice-to-proceed around Aug. 3.

The Oskaloosa City Council voted to award the Burlington Road reconstruction contract after staff reported the low bid totaled $893,853, which staff said came in approximately 17.6% below the engineer's estimate.

Staff presented the project scope: remove the existing surface of Burlington Road (South 15th to South 17th) and related segments, replace the water main in the same location, install storm sewer infrastructure, construct a 20-foot PCC roadway, and add sidewalk along the east side of South 15th Street. The engineer's estimate for Division 1 was recorded in the meeting as $772,455 and Division 2 at $312,575; staff reported the low bidder's allocation to the city at $636,888 and $296,965 to the Oskaloosa Municipal Water Department.

Staff recommended award to the low bidder (identified in the meeting record as Drish) and requested a $65,000 contingency administered by the city manager. The council moved, seconded, and approved the award by roll call; staff indicated a notice to proceed would be issued around Aug. 3 with an expected completion date in November 2026.

What’s next: staff will finalize contract documents, issue the notice to proceed pending execution, and administer the contingency for unforeseen circumstances.

Sources: Staff presentation and roll-call approval at the July 6, 2026 meeting.