Board approves athletic-complex change orders; contractor credit and timeline confirmed

Metcalfe County Board of Education · November 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Metcalfe County Board of Education approved change orders for the district athletic complex on Nov. 12, confirming a $4,548 credit from the contractor and updates on sidewalks, lighting, turf installation and completion timing.

The Metcalfe County Board of Education on Nov. 12 approved change orders for the district athletic complex, including a contractor credit of $4,548.

Facilities director Matt Shirley had told the board the change order tied to action item 5C would produce a $4,548 refund to the district. Shirley also outlined current construction progress: sidewalks around the track are being poured so the track can be paved; lighting was expected the following day; turf is scheduled to be laid later in the month; goal posts were due to arrive shortly; and the storage/utility building under the bleachers was nearly complete. Projected overall completion was given as June.

Robin McMurtrey moved to approve the change orders; Daniel Glass seconded and the board voted unanimously (5–0). The board did not add conditions or amendments to the change orders during the meeting and instructed facilities staff to continue coordination with contractors.