Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Geary County public works approves two new farm access points, updates on chip-seal and courthouse repairs
Summary
Public works presented multiple operational updates: the commission approved two access entrances on Milford Lake Road, received a chip-seal progress report, was told ROI LED lights had arrived and approved a courthouse roof repair proposal tied to an insurance claim.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Jeremy Myers, Geary County public works administrator, recommended approval for two new entrances on Milford Lake Road to provide pasture access. Myers said both locations were inspected, no site-distance issues were found, and a standard 18-inch culvert with end sections will be required; the commission moved, seconded and approved the request.
Myers also reported the county had about 2.5 miles remaining on this year's chip-seal route and that the chip seals were performing well. He said ROI's LED lighting materials had been delivered and a pre-install meeting with ROI and its subcontractor was scheduled for the following day.
On storm damage to the courthouse, Myers said a June storm damaged a copper ridge cap and some slate tiles. The county submitted an insurance claim and received Stanfield's estimate of $14,595.08; Myers said the insurer (K Camp) approved the proposal and a check for $9,595.08 will be issued after a $5,000 deductible. He requested authorization to sign the repair proposal and schedule work.
Myers also updated the commission on a USDA loan and grant package referenced in the record (transcript: "Bridal Development") — a $136,000 loan and a $197,000 grant — and said KDHE documentation remains in process before final loan paperwork is executed.
What happens next: public works will proceed with the required culvert/end-section work for the new entrances, coordinate ROI's pre-install meeting, and move forward with courthouse repairs upon final paperwork.

