District seeks board approval to use CMGC procurement for seismic and roofing work
Summary
Facilities staff told the board about recent capital projects and asked for authority to proceed with a construction-manager/general-contractor (CMGC) procurement approach for seismic work at Lincoln and a Redwood roof project to accelerate collaboration between designers and contractors while maintaining a competitive proposal process under ORS.
Get email alerts on the Facilities Procurement topic
No spam. Unsubscribe anytime.
District facilities staff briefed the board on capital maintenance, seismic projects and a recommended procurement method for high-complexity work.
The facilities presenter reviewed completed projects (playground upgrades, track lights funded with booster help, bleacher replacements, bathroom renovations) and outlined a backlog of seismic and roofing priorities, including a core roof replacement at Grants Pass High School and seismic work at Lincoln and Redwood.
Staff requested board authorization to pursue a construction-manager/general-contractor (CMGC) procurement process for the Redwood seismic/roof project and related work. Facilities staff explained that CMGC brings the contractor into design early to support value engineering, schedule acceleration and reduced risk during complex work at occupied schools. They emphasized the process will be competitive: the district will issue an RFP and evaluate proposals on qualifications and price rather than a simple low-bid ITB.
Board members asked about conflicts and fairness; staff said legal counsel reviewed the approach and that selection criteria and scoring would be public. The board later approved fact-finding and authorization to proceed with the CMGC procurement steps on the motion calendar.