Council reviews bids and priorities for road repaving and stormwater fixes
Summary
City staff described prioritized repaving and stormwater work on multiple local streets, possible savings via county bids and use of a Special Road District; timing and necessary stormwater inlets could push some work into 2027 if not scheduled now.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
City public-works staff (S1) briefed the council on planned road repairs, stormwater work and potential contracting options intended to stretch the city’s paving dollars.
S1 listed several streets being considered for repair — Leona, La Verne, Heinz, Kale (from Fulton to Jazz), Orchard, Beretta, and a segment of Soave from Pleasant Eye Road to Kale — and said some locations (Orchard and Beretta) require stormwater inlet work before asphalt can be laid, otherwise new asphalt would quickly fail. He said one contractor, Tandem, supplied a bid tied to Platte County pricing, which could save money and avoid a separate competitive bid process.
S1 warned that some projects risk slipping into 2027 if schedules or financing aren’t finalized; he also discussed the mechanics of coordinating with the Special Road District (outside agency) when additional funds or approvals are required. Council members discussed whether to request more funding from the Special Road District or to adjust the city’s allocation to keep projects on the 2026 schedule.
Public-works staff said they would return with finalized numbers and bid comparisons. The council did not record a formal contract award in the supplied transcript segments.
Next steps: staff to obtain detailed cost estimates, confirm whether Special Road District funds are needed, and return with scheduling/contract recommendations to the council.