Deputy Director Nate Sears reported substantial completion of the Rock Harbor Wharf project, the reopening of Nauset Estuary shellfishing, and a forecasted July 20 limited opening for Nauset Beach South to over‑sand vehicles under a Habitat Conservation Plan with special escort rules.
Get email alerts on the Natural Resources topic
No spam. Unsubscribe anytime.
Nate Sears, deputy director of Natural Resources, told the board the town has substantial completion of the Rock Harbor Wharf Improvement Project and invited residents to visit the working waterfront.
Sears said Nauset Estuary reopened to recreational shellfishing on June 12 after an earlier closure for a red‑tide harmful algal bloom, and that the shellfish department seeded roughly 600,000 additional quahogs.
On visitor access, Sears said Nauset Beach North’s resident over‑sand‑vehicle section opened June 12, spans about 0.333 of a mile and presently accommodates roughly 150 vehicles, with occasional off‑site staging when capacity is reached.
Looking ahead he forecasted limited, HCP‑governed access for Nauset Beach South “around July 20,” based on shorebird hatch dates and current conditions. Under the Habitat Conservation Plan with the U.S. Fish and Wildlife Service, Sears said each vehicle must have “a person over the age of 16 to walk in front of their vehicle to pass on fledged broods of piping plovers” during the roughly 10‑day HCP period, and that the town will coordinate timing with neighboring Chatham.
Sears also reminded residents that some town landings have parking restrictions from June 15 through Sept. 15 and said the required resident beach parking permit is available at the DPW sticker office from 9 a.m. to 1 p.m.; maps and regulations are posted on the town website.
The presentation closed with an offer to answer questions from the public; several board members and residents later praised the wharf project and seasonal staff who operate waterfront and parking services.