Mesilla commissioners discuss permit expiration, CID review delays and code clarifications
Summary
Commissioners and staff discussed inconsistencies in permit expiration timelines, CID review delays and potential code amendments; they agreed further work sessions will likely be needed to clarify when permit expiration should begin and how administrative processes should align.
Get email alerts on the Administration topic
No spam. Unsubscribe anytime.
At the May 4 meeting the Town of Mesilla Planning, Zoning and Historical Appropriateness Commission held a wide-ranging discussion about discrepancies in code language and administrative procedures affecting permit expirations, permit extensions and review timelines.
Economic & Community Development Director Eddie Salazar framed the issue, noting that many commercial projects remain active for extended periods because of engineering revisions, structural review requirements, utility coordination and state Construction Industries Division (CID) review timelines. Commissioners debated whether permit expiration periods should begin at initial PZHAC approval, at Board approval or after engineered plans are finalized.
Thomas Maese, representing the New Mexico Construction Industries Division, explained distinctions among historic appropriateness review, zoning review and structural code review, and underscored that separate reviews can create real delays in getting building permits finalized. Commissioners noted potential inconsistencies in administrative interpretation related to RV occupancy regulations, utility hookups and fence setbacks.
Commissioners and staff agreed that future work sessions would likely be necessary to draft clarifying amendments to Town code and administrative procedures to reduce delays and increase consistency in reviews.