Comcast says fiber build reaching Preston, aims for first home connections by February 2025
Summary
Comcast briefed the council that fiber construction is moving from Franklin toward Preston with company targets to complete the build by the end of 2025 and begin connecting homes by February 2025.
Get email alerts on the Broadband topic
No spam. Unsubscribe anytime.
Comcast representatives Joe Silverzweig and Kyle Weaver told the Preston City Council that the company’s fiber-optic project is moving through Franklin toward the city and that Comcast aims to complete construction by the end of 2025. The company indicated it hopes to begin connecting the first homes in Preston around February 2025 as crews progress along the planned route.
Officials said the build is moving quickly in neighboring areas and that Comcast expects to make fiber connectivity available to Preston residents as sections are completed. No formal action or city commitment was required at the meeting; the update was provided for council and public information.