Summary

The commission awarded multiple 2026 construction and supply contracts (aggregate base, pipe/fittings, curb and gutter), approved a six‑month‑per‑year $7,500/month electric golf‑cart lease amendment for two remaining years, and adopted Ordinances 1887 and 1888 and Resolution 2808 to implement engineering design and sidewalk standards. All votes were unanimous.

At its Feb. 10 meeting, the City of Pierre Board of Commissioners unanimously approved several staff‑recommended contract awards for 2026, amended a lease for golf carts at city facilities, and adopted new engineering design and sidewalk rules.

Staff recommended and the commission approved the following contract awards: a $93,000 award to B&B Equipment for the 2026 Aggregate Base Course; Schedules A and C of the Pipe, Fittings, Valves and Hydrants procurement to Milbank WinWater for $71,628.69 and Schedules B, D and E to Dakota Supply Group for $59,493.70 (staff noted one bid omitted an addendum acknowledgement and two read bids contained minor mathematical errors); and a $433,238 award to American Contracting and Consulting of Pierre for the 2026 Curb and Gutter Project. Caleb Huizenga and Scott Schweitzer (staff engineers) presented the items; Commissioner Johnson moved and Commissioner Reitzel seconded the awards, which passed unanimously.

Bryan Tipton, Park and Recreation Director, presented an amendment to the existing 50‑cart lease with EZGO and Miller & Sons that would allow the city to switch to electric carts for the remaining two years of the agreement. The amended lease sets the payment at $7,500 per month for the six months each year the course operates; the commission approved the amendment unanimously.

Nick Waters (City Engineer) presented Ordinance 1887 to adopt the City of Pierre Engineering Design and Construction Standards and Ordinance 1888 to amend Section 6‑3‑106 (sidewalk distances) by moving the list of exceptions into Appendix E; the commission adopted both ordinances on second reading unanimously. Waters also presented Resolution 2808 to adopt Appendix E; the commission approved the resolution unanimously. The ordinances and resolution will be published as required by city procedure.

Votes at a glance: • Consent calendar (minutes Feb. 3; personnel items; volunteer firefighter application; raffle request; claims) — moved by Commissioner Johnson, seconded by Commissioner Reitzel; unanimous approval. • 2026 Aggregate Base Course — award to B&B Equipment, $93,000; moved Commissioner Johnson; second Commissioner Reitzel; unanimous. • Pipe, Fittings, Valves and Hydrants — Schedules A & C to Milbank WinWater $71,628.69; Schedules B, D & E to Dakota Supply Group $59,493.70; moved Commissioner Johnson; second Commissioner Reitzel; unanimous. • 2026 Curb and Gutter Project — award to American Contracting and Consulting of Pierre, $433,238; moved Commissioner Johnson; second Commissioner Reitzel; unanimous. • Golf cart lease amendment (switch to electric for remaining two years) — $7,500/month for six months per year; moved Commissioner Reitzel; second Commissioner Johnson; unanimous. • Ordinance 1887 (Engineering Design and Construction Standards) — second reading and adoption; moved Commissioner Huizenga; second Commissioner Lerseth; unanimous. • Ordinance 1888 (amend Section 6‑3‑106; move exceptions to Appendix E) — second reading and adoption; moved Commissioner Huizenga; second Commissioner Lerseth; unanimous. • Resolution 2808 (Adopt Appendix E) — approval; moved Commissioner Huizenga; second Commissioner Lerseth; unanimous.

Several items noted by staff for the public record: one bid had a missing addendum acknowledgement (pipe/fittings procurement) and two read bids contained minor arithmetic errors that staff corrected before recommendation. The transcript does not record post‑award contract execution dates or additional commercial terms beyond award amounts.