Tippecanoe County approves $3.47 million amendment to Avenue Inc. contract for Bridge 530 and Calvert & Yeager signal

Tippecanoe County Commissioners · July 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved Amendment No. 1 to the Avenue Inc. agreement, finalizing two incomplete Phase 1 segments with guaranteed maximum prices of $2,271,000 (Bridge 530) and $1,200,000 (Calvert & Yeager signal) and completion dates in November and December.

Tippecanoe County commissioners approved Amendment No. 1 to an agreement with Avenue Inc. on July 20, finalizing two remaining Phase 1 segments of a construction program.

Doug explained the amendment sets a guaranteed maximum price (GMP) of $2,271,000 for Bridge 530, with a construction schedule targeting completion by November, and a GMP of $1,200,000 for the traffic signal at Calvert and Yeager, targeting completion by December. Together the two GMPs total $3,471,000.

A commissioner moved to approve the amendment and the chair seconded; the board approved the motion by voice vote.