Commissioner outlines FDOT tentative 2025–2030 work plan projects affecting the Keys

Key Colony Beach City Commission · December 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioner Tom Harding summarized key elements of the Florida Department of Transportation’s tentative 2025–2030 five‑year plan, including repairs to Vaca Cut Bridge (2027), Channel 5 Bridge (2026), a Snake Creek Bridge proposal to convert to a fixed bridge, Bahia Honda repairs and long‑term work on the old seven‑mile bridge ahead of a planned replacement in 2035.

At the Dec. 16 townhall, Commissioner Tom Harding reviewed the Florida Department of Transportation’s tentative 2025–2030 Five‑Year Work Program and described multiple bridge and roadway projects that could affect Key Colony Beach and nearby Keys.

Harding identified repairs scheduled for the Vaca Cut Bridge in 2027 and Channel 5 Bridge in 2026, and said there is a proposal to convert the Snake Creek Bridge to a fixed bridge. He said Bahia Honda is slated for repairs and that FDOT will continue small repairs to the older seven‑mile bridge to keep it stable until a planned replacement about 2035. Harding said FDOT requires bridge replacements after about 50 years and noted that Sadowski Causeway does not fall under FDOT responsibility and would remain the city’s obligation.

Harding reported that FDOT has been open to providing details and that counties and municipalities are still awaiting formal project approvals, which are expected in July 2025 under the FDOT schedule he cited. He also noted that nearby municipalities, including Marathon, have received funding for shoreline and beach projects such as Cocoplum and Sombrero Beach.

No formal regional funding decisions were taken at the townhall; Harding presented the summary to inform residents and to flag infrastructure items the city may need to monitor or coordinate on with county or FDOT staff.