District updates classrooms, gyms and athletic field as summer projects near completion

Brown County School Corporation Board · July 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported progress on high-school HVAC and restroom turnover, Van Buren chilled-water and VAV installations, tennis‑court resurfacing, and athletic-field work including drainage and scheduled concrete pours for bleacher footings July 30–31.

District operations staff provided a multi-site construction update July 20, reporting near-complete HVAC and lighting upgrades at the high school and Van Buren, tennis‑court resurfacing, and significant progress on the new athletic field.

The district’s construction lead said restrooms at the high school are ready except for fixtures and require final occupancy approval before students can use them. Gym fabric ducting and new return-air systems are installed, LED lighting is complete and science‑wing HVAC and ceilings have been finished and handed to custodial staff.

"We have restrooms that are getting ready to be turned over," the construction lead said, adding the project still needs final fixture installation and occupancy sign‑off. He said the main‑gym supply/return duct connections remain to be completed but that most work is finished.

At Van Buren, three new air handlers, chilled‑water equipment and 32 variable air volume (VAV) boxes are installed; ceiling replacement and LED lighting are about 90% complete and the district is moving furniture back into classrooms. The construction lead said the project team expects teachers to regain access by the target date (Friday, per the update), subject to final cleaning and protection removal.

On the athletic complex, staff reported the perimeter field drain is complete, rock grading for the track is about 80% finished, and contractors are scheduled to pour concrete for bleacher and press‑box footings July 30–31. The update described post‑tension cabling in the concrete and a recently installed retaining wall along the northeast corner; a small turnaround/parking area will remain near the barn.

Tennis courts received a two‑phase resurfacing and repainting that removed cracks and restored playing lines; staff said the repairs make the courts playable and more attractive for play. The district also plans to publish an FAQ and photos on the website so community members can track project progress without attending board meetings.

Staff emphasized next steps: finish remaining fixtures and duct connections, complete final inspections and secure occupancy approvals before the start of school. The construction lead and central office staff did not announce specific final‑occupancy dates in the transcript beyond the target timeline the team has shared with teachers.