Preston defers $750,000 4th East street repair; approves $50,000 for testing and engineering
Summary
Council agreed May 12 to defer a $750,000 4th East street repair project until summer 2026 and approved roughly $50,000 now for testing and engineering so bidding can occur in February 2026 and construction begin when school is out.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The Preston City Council voted on May 12 to defer a planned $750,000 4th East street repair project and to use approximately $50,000 from the current budget for core sampling and engineering work.
Councilmember Terry Larson explained that preparatory testing would delay equipment mobilization until at least Aug. 1, meaning the full construction could not be completed before the new school year; Larson recommended proceeding now with testing and engineering and rebidding the project in February 2026 so construction could start immediately after school ends. The motion (seconded by Councilmember Brent Dodge) to reallocate about $50,000 for testing, defer the $750,000 construction budget into 2025–26, and return about $700,000 to the general fund passed unanimously.
Council documents estimate the physical repairs will take at least 50 days once construction begins; staff will return with engineering reports and a schedule ahead of the February bid date.
What happens next: staff will complete the core sampling and engineering tasks this year and prepare the project for bidding in February 2026.