Hesston council approves $39,125 change order to apply subgrade modification to trail north of the pond
Summary
The Hesston City Council approved a change order to apply a subgrade modification to the full 1,200 linear feet of the trail section north of the pond at a lump-sum cost of $39,125 per PLI's 5/15/26 proposal; the vote was 4-0 with one abstention.
Get email alerts on the Public Works Trail topic
No spam. Unsubscribe anytime.
The Hesston City Council on May 18 approved a contractor change order to extend a subgrade modification to the full 1,200 linear feet of the trail section north of the pond at a cost of $39,125, citing lump-sum pricing in a PLI proposal dated May 15, 2026.
Council member Larry Fuqua moved to apply the subgrade modification to the full trail length north of the pond at a cost of $39,125; Council member Brad Unruh seconded. The motion carried 4-0 with Council member Michael Wallace recorded as abstaining.
The minutes identify the action as based on PLI’s 5/15/26 proposal and record the cost and scope (1,200 linear feet) but do not include additional contract details such as funding source, project timeline, or contractor start/completion dates. The minutes also do not state the reason given for Michael Wallace’s abstention.
The change order was recorded during a special meeting that included a budget work session and other agenda items.