Proctor Selectboard approves $395,708 in Synagro invoices for sewer sludge work; lagoon repairs planned
Summary
The Town of Proctor Selectboard approved Synagro invoices totaling $395,708.20 to pay for sludge removal and related work at the wastewater treatment facility; the board recorded lagoon damage to be repaired with held-back funds and said the bond will reimburse the sewer account once complete.
Get email alerts on the Sewer topic
No spam. Unsubscribe anytime.
The Town of Proctor Selectboard approved payment of two Synagro invoices totaling $395,708.20 during its Nov. 24 meeting, a move to cover sludge removal work and related repairs at the town wastewater treatment facility.
Selectboard member Albert Wenta made the motion to “sign and approve for $312,094.57 and $83,613.63,” which was approved by the board. The invoices are to be paid from the sewer account because bond funds tied to the project have not yet completed processing; the board noted the bond was approved and the sewer account will be repaid when those funds clear.
Aldrich & Elliott reviewed the WWTF sludge project and reported uneven sludge distribution: Lagoon 1 contained less sludge than expected while Lagoon 2 contained more and suffered structural damage described in the packet as a torn linear. The Selectboard said holdback funds will be reserved to finance summer repairs and that Lagoon 2 will be closed for the winter season while repairs are scheduled.
The board postponed a fuller WWTF discussion until Dec. 9 in hopes a State representative will attend the meeting to review the project details and approval criteria. The motion to approve the Synagro invoices was recorded as approved by the board; no roll-call vote totals were provided in the transcript.