Stormwater Improvement Project #1 set to begin June 1; castings delay reported
Summary
WithersRavenel held the pre-construction meeting for Stormwater Improvement Project #1 (Coquina–Carteret Drive). Maintenance/Zoning Supervisor Mike Haber reported a 6–8 week delay in castings; construction is scheduled to start June 1, weather permitting.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Maintenance and Zoning Supervisor Mike Haber reported that WithersRavenel held the pre-construction meeting for Stormwater Improvement Project #1, covering work on Coquina and Carteret Drive. Haber said the project is scheduled to start June 1, subject to weather, but noted a 6–8 week delay in delivery of castings for drainage tiles.
Haber told the board he was monitoring related issues — including a separate sinkhole on Country Club Drive — and will coordinate construction timing as material deliveries and weather allow. No vote was taken; the board received the project update and will monitor progress ahead of the June 1 start date.