Summary
The special magistrate found a violation for construction duration at 118 Marlin Drive under town code and imposed a $150 per day fine beginning July 7, 2026; the magistrate said she lacked authority to grant a late extension and encouraged the owner to seek mitigation after compliance.
Get email alerts on the Construction Duration topic
No spam. Unsubscribe anytime.
The magistrate heard argument on whether the two-year construction duration had elapsed for 118 Marlin Drive. Town staff said the notice of commencement and inspection history indicated construction had begun in 2024 and that the two-year window has passed; staff recommended a per-day fine for continued noncompliance. Owner Ara Garibian acknowledged delays tied to design and said the project had restarted with a new design team.
Magistrate Amity Barnard determined that under the town code she did not have latitude to grant an extension after the statutory window had passed and, finding a violation of section 67-52, ordered a $150 per day fine to begin on 07/07/2026 until construction is complete and the property is closed out; she advised the owner to compile documentation of good-faith efforts to seek mitigation when in compliance. "I don't think I have the latitude to give you the extension," the magistrate said when denying an on-the-spot extension request.