Council approves final payment for accessible quadrant curb improvements
Summary
Final pay request of $75,003.44 (plus a small change order) to CWF Concrete & Masonry was approved to complete accessible quadrants (truncated domes and curb ramps); staff said favorable bids allowed additional quadrants to be added and the project is complete.
Get email alerts on the Streets topic
No spam. Unsubscribe anytime.
Council approved pay request number 2 and change order number 2 to CWF Concrete & Masonry totaling roughly $75,003.44 to complete the city's accessible quadrant improvements.
Destin told council the work covered curb-corner truncated domes and slopes at block corners; favorable bids allowed staff to order additional quadrants, increasing total spend toward a planned $250,000 budget (staff estimated spending about $238,000 so far). Staff recommended approval of the final payment and change order, and the council approved the motion by roll call.