Contractor says construction on schedule; doors projected late August

Watertown Unified School District Fiscal Committee · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

JP Cullen reported demolition and plumbing work complete, painting and finishes underway, and long-lead doors due around Aug. 20–24 — a final critical path item before punch-list work and occupancy.

JP Cullen’s project manager told the committee that demolition is complete, underground plumbing for the new adaptive bathroom is finished, and most new walls are framed and taped. The team has moved into painting, electrical and mechanical finishes and expects painted rooms and flooring to start appearing within a week.

Staff emphasized the delivery window for long-lead doors as the next critical path; the contractor said door deliveries are currently slated for Aug. 20–24. Committee members said the schedule “looks good” based on photos staff circulated and expressed confidence in the contractor’s superintendent and schedule adherence.