Stonington reviews portable installation and pauses second-floor remediation amid insurance concerns

Stonington Board of Education · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff reported portable classroom installation is ready for final approval with a tentative June 5 start to address middle-school crowding; second-floor remediation will be paused while monitoring continues and the Board of Finance raised insurance concerns.

District administrators told the board that portable-classroom installation is ready for final approval and the tentative construction start date is June 5. The portables are intended to alleviate crowding at the middle school; Acting Superintendent Tim Smith said it is imperative they be ready before the fall semester.

Administrators also reported that bids for the District Office second-floor slab came back higher than expected and were rebid; three new bids were closer to original estimates. The district will pause second-floor remediation and have Fuss & O'Neil continue monitoring for building shifts. The Board of Finance raised concerns about insurance coverage related to the project; staff said they will address BOF concerns and report back.