Project manager: substantial completion Dec. 17; move-in and first day of school set for winter 2027 window

Whitman-Hanson Regional School District School Building Committee ยท July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager reported substantial completion of the new middle school is targeted for Dec. 17, with move-in between Dec. 18, 2026 and Feb. 11, 2027 and first day of school Feb. 22, 2027; project staff outlined move-management steps, soft-opening and a future ribbon-cutting.

Project staff told the committee the construction schedule remains focused on a Dec. 17 substantial completion date and described a move-in and occupancy plan spanning December 2026 through February 2027.

The project manager said substantial completion is targeted for Dec. 17. Staff training and system activation will follow; move-in dates were listed as Dec. 18, 2026 through Feb. 11, 2027, with staff unpacking around Feb. 11 and the first day of school on Feb. 22, 2027. Phase 2 substantial-completion (demo and fields) was referenced with a later date for follow-on work.

Committee members discussed logistics including a soft opening/open house for the community, timing of a formal ribbon-cutting ceremony (committee members suggested an official event in the fall and a soft opening before school starts), move-management coordination meetings starting in August, and compensation or scheduling for staff who might need to move during school vacation periods.

Project staff also reviewed on-site progress photos showing drywall finishing, auditorium and gym work, and new fencing along the retaining wall. Staff noted that the team had been progressing quickly week-to-week and that final cleaning and punch-list work were underway.