After $190M shortfall, county and town propose scaled-down Hilton Head bridge package

Beaufort County Transportation Committee · March 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facing an approximate $190 million funding gap, county and town officials proposed a repackage that keeps $300 million in combined funds — including a $120 million DOT grant — to build a three-lane‑designed eastbound bridge (striped as two lanes initially) replacing the failing single eastbound span; the plan will be presented to the State Infrastructure Bank next week for approval.

Jared told the committee the Hilton Head bridge project faces a significant funding shortfall and that county and town leaders have jointly agreed on a repackage they will ask the state to approve. "What's transpired over the last couple months ... we have a $190,000,000 shortfall," Jared said, and county and town officials have "developed and agreed on a plan" to propose a scaled-down project to the State Infrastructure Bank.

Under the repackage Jared described, the proposal would retain approximately $300 million in combined funding (county funds plus a $120 million state DOT grant) to replace the eastbound span with a new structure designed for three lanes but initially striped as two lanes. Jared said the plan addresses the immediate safety and structural concerns of the existing single-span eastbound section and is designed for a 75-year lifespan: "It's not the full 6 lane bridge that we had envisioned, but it does address a lot of the concerns ... The bridge is designed for a 75 year lifespan." The county and town will meet next week with the state infrastructure bank and DOT; if the bank approves the package, DOT would move forward with the redefined project. If the bank refuses or approves less than the requested $120 million, the county and town would re-evaluate options, which could include a DOT-only replacement of the single span.

Committee members discussed whether federalization or a future sales-tax measure might be used to fund the remaining lanes; staff noted the earliest a future county sales-tax measure could be filed is 2026 and that packaging clearly defined projects could improve voter support for future funding rounds. No final local decision was made at the meeting; committee members asked for continued updates and clear timelines for the State Infrastructure Bank review and DOT response.