Wastewater task force presents $7.3M—$11.2M options for Brownsville-area systems; phasing considered

Jericho Selectboard · July 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Consultants presented two options for a Brownsville-area wastewater system: a moderate plan (~$7.3M; ~37,500 gpd) and an enhanced plan (~$11.2M; ~60,500 gpd). The task force is evaluating phasing to maximize gallons-per-dollar and preparing community outreach.

The town's wastewater task force reported consultant DuBois & King provided site configurations and cost estimates for potential wastewater systems near the Brownsville Middle School area. The task force explained a moderate configuration (sites A, C, D, E) would provide roughly 37,500 gallons per day capacity at an estimated cost near $7.3 million and could serve roughly 153 dwelling-unit equivalents. An enhanced configuration would provide about 60,500 gallons per day capacity at an estimated $11.2 million and an estimated 288 dwelling-unit equivalents; once capacity passes certain thresholds additional filtration and systems are required, which drives per-unit costs.

Task force members emphasized phasing options (selecting sites to maximize gallons-per-dollar while minimizing up-front cost), outreach to community groups and staged recommendations back to the board. The task force plans further outreach and will refine the mix of sites and expected phasing to present options that optimize capacity and cost.