Workforce housing project in limbo as environmental findings prompt redesign and possible earmark extension
Summary
Staff said the workforce housing project is under redesign after Phase I/II environmental work found unbuildable areas (a log pond and a former burner area); the city plans further consultant work and may request another extension on a 2020 earmark.
Get email alerts on the Housing topic
No spam. Unsubscribe anytime.
Planning staff told the commission the workforce housing project remains in preliminary design and is "kind of in limbo" while consultants complete environmental and geotechnical work. Staff said Phase I and Phase II work identified the log pond and a former burner area as unbuildable, prompting a redesign that preserves those spaces as open area to meet density and open‑space requirements.
Staff also noted the project’s federal earmark, filed in 2020, has required at least one extension and that another extension may be necessary depending on construction timing. "We have already worked on the redesign… knowing the log pond with the geotech report and what we've learned so far with the environmental phase 1 and phase 2," staff said; they added consultants will work through environmental details and the matter may move up the governor's office as needed. Staff indicated more information will be available after consultant meetings.