Developer says permits and subcontractors will shape timetable for proposed food-cart village
Summary
Lucas, representing Lucas Main Construction, told the agency the project timetable depends on permitting and subcontractor availability and that market prices have been stable; he said the developer will invoice monthly under the proposed reimbursement line of credit.
Get email alerts on the Project Timeline topic
No spam. Unsubscribe anytime.
At the agency meeting, Lucas (the developer representative) updated members on work since the last meeting and described contingencies that will shape the construction timeline. Asked to summarize changes, Lucas said the plans remain preliminary and that permits and subcontractor scheduling will determine the schedule. "Prices have not changed," Lucas said, describing the market as "kind of volatile" but not showing recent increases.
Lucas explained contract clauses the developer anticipates, including a weather clause and provisions covering subcontractor replacement when necessary. He said the developer expects to submit monthly invoices under the line-of-credit/reimbursement arrangement and noted the project will be fine-tuned once permits and final dates are known. Staff confirmed the developer will coordinate timelines with the agency when permits are secured.