Committee records about $507,000 in change orders, asks for review of $17,000 PCO
Summary
The committee was told five formal change orders totaling approximately $507,000 have been executed, including roughly $100,000 for data cabling and a proposed PCO 75 of about $17,000 for floor underlayment that members asked staff to review further.
Get email alerts on the Budget topic
No spam. Unsubscribe anytime.
Committee members reviewed the project's change-order log on June 9 and were told five formal change orders have been executed to date, totaling approximately $507,000. Major line items called out in the minutes include data cabling at about $100,000, the solar installation at about $60,000, and office additions exceeding $20,000.
The Committee reviewed a proposed change order, PCO 75, for about $17,000 to install a new floor underlayment to ensure proper adhesion of flooring materials. Members agreed that additional review of pricing and scope is needed before moving to approval, though the amount appeared in line with expectations.