Deerwood council adopts assessments for 2026 street project

Deerwood City Council · May 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Deerwood City Council unanimously approved Resolution 2026‑17 adopting assessments for the 2026 Street Project after a public hearing where engineers explained a switch to full‑depth reclamation (FDR) and residents asked about stormwater and utility longevity.

The Deerwood City Council on May 11 adopted assessments for the 2026 Street Project, approving Resolution 2026‑17 by unanimous vote. Member Aulie moved the measure and Member Ingersoll seconded; Mayor Millsop and Members Aulie, Ingersoll and Voller voted aye.

City Engineer Alex Voit (SEH) told the council that geotechnical testing showed the streets require full‑depth reclamation (FDR) rather than a mill‑and‑overlay. "The geological testing came back as it needed the FDR rather than the Mill and Overlay," Voit said. During the public hearing residents asked whether water and sewer lines would need replacement within the assessment period; the Public Works Foreman responded that "the water and sewer lines will be good for another 40 to 50 years." The council set a special follow‑up meeting for June 1 to continue project coordination.