Committee details reuse, mothball and demolition options for Center and Hall Memorial, estimates carrying costs

Willington School Building Committee · July 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Presenters said the state will reimburse Hall work tied to the project but not Center Elementary; they estimated mothball carrying costs of $75k–$100k per year and gave high-level conversion budgets (light office ≈$8.2M, senior housing ≈$16M).

Consultants and committee members described options for Center Elementary and Paul Memorial if the district consolidates at Hall or a new site. They said the state will reimburse work associated with Hall Memorial if it is part of the school project, but Center Elementary (a separate parcel) would not be reimbursed under the project scope.

The team estimated carrying or "mothball" costs for Center at about $75,000–$100,000 per year to keep it wind- and weather‑safe, and provided high-level conversion budgets: modest office conversion roughly $8.2M and more extensive residential conversion (senior housing) around $16M. Jeff Wazinski said the town has several years before students would move to a new facility and that mothballing is a feasible short-to-midterm option while the community seeks reuse decisions. "It's about 75 to maybe $100,000 a year, for kind of carrying cost," he said when describing the estimate for keeping Center on the site.