Board gives 601 South Hackberry 90 days to complete repairs; owner says work underway
Summary
The board found 601 South Hackberry repairable and ordered repairs within 90 days after the owner’s representative said permits had been pulled and a contractor retained; permits from February will expire in August unless work is completed.
Get email alerts on the Repair topic
No spam. Unsubscribe anytime.
The Building Standards Board voted 7–0 to order repairs at 601 South Hackberry to be completed within 90 days, after Development Services and the owner’s representative detailed the property’s repair status and recent permit activity.
Cynthia Santana presented photos showing extensive fire and smoke damage, missing siding and sagging porch structure; she told the board that a re-roof and building repair permit were issued in February 2026 and will expire in August 2026. "The building permit for a re roof and building repair were issued in February," Santana said. Staff recommended repair rather than demolition because the owner had pulled permits and demonstrated an ability to pursue work.
Owner representative Angela Jarman said she had secured a contractor and paid half the fee; the contractor is scheduled to start work and the owner aimed to complete repairs by August, when current permits expire. Board members pressed for a clear timeline and confirmation of electrical and plumbing work; the board then ordered repairs within 90 days and required the property remain secured and free of trash and debris. The motion passed unanimously.