State Road rebuild moving fast; kitchen modernization to be bid for next summer
Summary
Staff said the State Road School addition and renovation is near completion of many external elements and will require heavy logistics (eight rental trailers) for summer interior work; the kitchen upgrade will be bid this fall and built next summer.
Get email alerts on the State Road School topic
No spam. Unsubscribe anytime.
Staff gave an update on State Road School construction, showing where the masonry, foam insulation and brick facade work stand and presenting renderings alongside current construction photos. Presenter said the project touches nearly every space: "literally every single room will be touched this summer," and described a plan to rent eight utility trailers to move furniture out and back during two-week windows.
Staff said solar panels at State Road will number about 110 and are expected to offset roughly 28% of that facility's utilities; they noted roof area and proximity to woods limit additional panels. The kitchen modernization will not be done this summer; staff plans to put that project out for bid in the fall with construction next summer and will add a refrigerator-freezer and remodeled service lanes to improve student flow.
Staff also described planned LMC changes (filling a pit, adding a conference room and reconfiguring the circulation desk) and emphasized the heavy internal construction schedule that makes precise timing critical.