District staff present $2.71 million capital plan, say referendum cut $29 million from backlog
Summary
La Crosse School District staff presented a $2,712,500 capital-improvement snapshot at a May 4 workshop, outlining school-by-school projects and saying the prior referendum removed roughly $29 million from the district's capital backlog.
Get email alerts on the Capital Budget topic
No spam. Unsubscribe anytime.
La Crosse School District staff presented the district's FY capital-improvement snapshot at a May 4 Board of Education workshop, saying the current total for this year is $2,712,500.
"The total for this year is $2,712,500," the presenter said, and added the district has re-scoped older projects after a referendum that removed about $29 million from the capital improvement book. The presenter described the removal as a way to "right-size" the district and focus remaining capital dollars on active schools.
The workshop covered a wide range of projects across elementary, middle and high schools: auditorium renovations at Central High; HVAC, roof and kitchen work at State Road; geothermal wells and solar panels at Hogan Elementary; playground and flooring replacements; and district-wide safety and access-control upgrades. Staff emphasized timing is often selected to capture lower bids, noting many projects are planned 12 to 18 months in advance.
Board members asked targeted questions on scheduling, ADA compliance and budgeting. After the workshop presentation, the board voted to move into a closed session to consider a superintendent evaluation under Wisconsin Statute 19.85(1)(c).