Residents press township for repairs after retention‑pond failures; developer commits temporary fixes

Board of Commissioners, East Pennsboro Township · July 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Residents showed video of recurring stormwater failures tied to a developer‑maintained pond on Oyster Mill Road and pressed the board for a timetable. Township staff said a re‑engineered plan was submitted, the engineer approved it, and the developer committed to a temporary remedy within about two weeks.

Residents from Oyster Mill Road told the board their road and private properties continue to be damaged by stormwater from a nearby retention pond and pressed for immediate repairs.

Amy Burkheimer presented video and testimony, saying the 2012 storm‑water maintenance agreement required semiannual inspections and that inspection reports could not be located. "These repairs are a need, not a want," she said, and urged the board not to allow the developer to control the timeline for fixes.

Township staff and the solicitor reported the developer submitted a re‑engineered plan the previous day and that the township engineer approved it; the developer had ordered permanent components but committed to install a temporary structure for the Wurn Alley Basin while parts are delivered. Solicitor Coin indicated the temporary fix should be installed "relatively soon," with staff adding the developer said it would be within two weeks of their meeting.

The board asked staff to forward the township’s cost estimate (staff cited roughly $10,000 in immediate roadway repairs) to the developer for review and to continue coordinating with FEMA where applicable. No enforcement judgment or penalty was adopted at the July 15 meeting.