Summary
The Board approved two purchase orders with Central ISG: $16,000 for hydraulic cylinder actuator replacements in the high service pump station and $30,000 for replacement in the low service pump station. Staff said one high-service cylinder is leaking and one low-service pump is intermittently failing; low-service repairs are expected to take 4–6 weeks.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
On July 15 the Board of Control approved two separate Central ISG purchase orders for hydraulic cylinder actuator replacements at the Lorain Water Purification plant. The high service pump request was for $16,000 ($14,525 plus contingency) after Central ISG was the sole bidder; staff said one cylinder is leaking and the other is failing to open and close, which could cause flooding or pump/motor damage if not addressed.
The Board also approved a $30,000 purchase order ($27,548.99 plus contingency) for a hydraulic cylinder actuator in the low service pump station after operators reported intermittent discharge valve failures on the most-used pump. Staff estimated the low service repair will take four to six weeks and said operators are monitoring plant operations while the repair is scheduled. Mayor Jack Bradley moved to approve both requests and Safety/Service Director Rey Carrion seconded; both motions carried unanimously.