Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Waterline Replacement topic
No spam. Unsubscribe anytime.
Tilden waterline fails pressure test; town investigators to probe loss of holding pressure
Summary
Work on Richmond’s Tilden waterline neared completion, but a pressure test failed to hold the required 195–200 psi and the line lost pressure, prompting further investigation and delaying final connection work.
Get email alerts on the Waterline Replacement topic
No spam. Unsubscribe anytime.
Contractors reported that the new Tilden waterline had been filled and brought up to test pressure but did not hold the required range for the two-hour test. "It built up to 200; it slowly dropped down to 180 and then it went to zero," a staff update said, and crews paused to determine whether there was a burst, poor connection, or other installation issue.
Commissioners were told crews were attempting to locate an existing repair at the far end of Cochran Road before making additional connections. Staff also said the Bridge Street connection work will be pressure-tested and flushed sequentially to tie into the new line; the timetable for finishing those segments depends partly on utility conflicts uncovered during excavation. The commission requested continued contractor updates and a follow-up report on the pressure-test findings.

