Developer: Eversource impact study shows no major upgrades needed; interconnection agreement still pending
Summary
Developer told the task force Eversource’s system-impact review indicated no circuit upgrades and that the project may interconnect with a new service and a recloser. The facility study and final interconnection agreement were not yet complete.
Get email alerts on the Interconnection topic
No spam. Unsubscribe anytime.
Developer representatives told the task force they have an Eversource system-impact response indicating the proposed array does not require major distribution upgrades and that, as described in an email exchange, the project could interconnect with a new service and a recloser. The team said it has not yet received a final facility study or a signed interconnection agreement.
“We have an email indication from them that we can install the system with just a new service and a recloser,” the developer said, adding that a formal facility study and the interconnection agreement will follow. Task force members asked whether a facility study would be required; the developer said in similar recent projects a facility study was often not required when an impact study passes, but cautioned a final report is still outstanding.
The developer committed to sharing the facility study and any interconnection agreement as soon as they are received. The task force noted that Eversource responses are central to project cost and scheduling and asked to be kept updated.
Next steps: developer to circulate facility-study results and the interconnection agreement when available and to track any impacts to the permitting and construction schedule.